Fictional example · Decision needed · VP · Q1 build order

Build SSO in Q1, bulk export first in Q2

Approve SSO for Q1 to unblock $780k of enterprise pipeline, plus a one-week CSV stopgap for the top 20 export requesters. This sets Q1 build order only.

Q1 has room for SSO or bulk export, not both

Enterprise prospects need SSO to pass security review; current customers need a way to get their data out.

Decision criteria, in a proposed order (the notes don't rank them):

  1. New revenue unblocked
  2. Existing revenue protected
  3. How many customers ask for it
  4. Effort and schedule risk

SSO gates $780k of pipeline; export cost us $64k

Pipeline is unweighted and not yet won. The $64k is revenue already lost to churn.

Bars to scale: enterprise pipeline $1.2M; SSO-blocked pipeline $780k (65%); churn citing data export $64k ARR Enterprise pipeline, 14 deals: $1.2M ARR SSO-blocked, 9 deals: $780k (65%) Churned citing "can't get data out", 3 customers: $64k ARR

SSO leads on revenue; export leads on demand and speed

CriterionSSO in Q1, with CSV stopgapBulk export in Q1
1. New revenueUnblocks 9 deals, $780k pipelineNot tied to pipeline in our data
2. Existing revenueStopgap for top 20 requesters; full export waits for Q2Fixes the reason 3 customers left ($64k ARR)
3. Demand9 of 14 enterprise deals212 tickets last quarter; 38% of feedback requests
4. Effort and risk6 weeks × 2 engineers, plus 1-week stopgap; outside review needed4 weeks × 2 engineers; no outside dependency

A one-week CSV stopgap bridges export until Q2

Plan in weeks, to scale: Q1 SSO 6 weeks then CSV stopgap 1 week, with outside review booked at the start (2 to 3 week lead time); Q2 starts with bulk export, 4 weeks Q1 Book outside security review: 2–3 week lead time SSO · 6 weeks · 2 engineers CSV stopgap · 1 week Q2 Bulk export · 4 weeks 02468 weeks

Stopgap staffing and its exact slot in Q1 are open.

SSO first means export requesters wait one more quarter

The outside review's lead time is the main risk

Approve SSO for Q1 and bulk export to lead Q2

VP decision: Q1 builds SSO (2 engineers, 6 weeks) plus a 1-week CSV stopgap for the top 20 export requesters; bulk export starts Q2. Needed in time to book the outside review, which has a 2–3 week lead time.

Commits: two engineers' Q1 time and booking the review. Open: review cost, stopgap staffing, the rest of Q2.

Sources: enterprise pipeline and security-review requirements; last quarter's support tickets, in-app feedback widget and exit surveys; engineering estimates. The company and every figure are fictional. Illustrative example.