Alder Lane mural
Fictional project · Weekly sponsor brief for Celia
Current forecast · Decision required
The mural is forecast
£300 over budget.
£4,250 has been spent, but £4,450 of future work remains. The £8,700 total exceeds the entire authorised budget, including contingency. The colour study is accepted; no wall painting is complete. [M2–M4]
The money still required changes the position
£4,250
Actual spend to cutoff
£4,450
Forecast future costs
£8,700
Current forecast total
£300 above the £8,400 limit
The £8,400 limit includes the £600 contingency. The notes do not confirm whether it has been released. [M1–M3]
Future costs: equipment £1,650 · artist fees £1,900 · materials £900. Actuals include all recorded invoices; the future estimate does not double-count them. [M2, M3]
| Reporting cutoff | Actuals | Future costs | Total |
|---|---|---|---|
| 2 October | £3,100 | £4,700 | £7,800 |
| 9 October | £4,250 | £4,450 | £8,700 |
Last week’s £600 headroom has become a £300 overrun. Actual spend rose £1,150; total forecast rose £900. [M1–M3]
Why the total forecast rose
£900 more than last week
Suki attributes the increase to the firm equipment quote and extra paint for the revised colour study. Other assumptions are unchanged. [M3]
+£650Equipment
+£250Extra paint
Two choices for Tuesday
Neither option is approved
Without a recorded choice by 12:00 on 13 October, Suki will hold the 14 October paint order. Any resulting completion-date movement is unquantified. The £450 saving is an option, not money already saved. [M4, M5]
Last week’s commitments
- Colour studyComplete
- Oren finished on 7 October as promised. Celia confirmed on 8 October that it matches the agreed design. This accepts the study, not the mural. [M1, M4]
- Equipment quoteComplete
- Suki obtained the firm quote by 9 October as promised. Remaining hire is £1,650, replacing the £1,000 allowance. [M1, M3]
- Invoice reconciliationComplete
- Kit reconciled invoices on 8 October as promised; Friday’s actual spend is £4,250. [M1, M2]
- Revised forecastProvided
- Celia’s requested revision is available above. No budget increase or spend beyond the limit has been authorised. [M1–M3]
- Caption wordingStill open
- Expected last week, but no owner or deadline was recorded. Oren will raise it at Monday’s team meeting; ownership of final wording remains unassigned. [M1, M4, M5]
Separate uncertainty from the overrun
The £300 overrun is already in the forecast. A further coat is a different, unpriced risk: all estimates assume no coat beyond the revised paint quantity. If another coat is needed, materials costs may rise; no price is supplied. [M3, M5]
What the border option establishes
Oren says a simpler border would preserve the central image. It still changes the agreed design. There is no measured evidence of residents’ preference for it. [M4]
Next actions
Mon 12 Oct: Oren brings the caption question to the team meeting; final wording owner remains open.
Tue 13 Oct, 12:00: Celia records the design and funding choice.
Wed 14 Oct: Suki orders remaining paint only after that choice.
Fri 16 Oct: Kit refreshes the forecast. [M5]