Alder Lane mural

Fictional project · Weekly sponsor brief for Celia

Week of Monday 5–Friday 9 October 2026
As of Friday 9 October 2026, 17:00
Goal: agreed wall design by 30 October · £8,400 authorised

Current forecast · Decision required

The mural is forecast
£300 over budget.

£4,250 has been spent, but £4,450 of future work remains. The £8,700 total exceeds the entire authorised budget, including contingency. The colour study is accepted; no wall painting is complete. [M2–M4]

The money still required changes the position

£4,250

Actual spend to cutoff

£4,450

Forecast future costs

£8,700

Current forecast total

£300 above the £8,400 limit
The £8,400 limit includes the £600 contingency. The notes do not confirm whether it has been released. [M1–M3]

Future costs: equipment £1,650 · artist fees £1,900 · materials £900. Actuals include all recorded invoices; the future estimate does not double-count them. [M2, M3]

Reporting cutoffActualsFuture costsTotal
2 October£3,100£4,700£7,800
9 October£4,250£4,450£8,700

Last week’s £600 headroom has become a £300 overrun. Actual spend rose £1,150; total forecast rose £900. [M1–M3]

Why the total forecast rose

£900 more than last week

Suki attributes the increase to the firm equipment quote and extra paint for the revised colour study. Other assumptions are unchanged. [M3]

+£650Equipment

+£250Extra paint

Two choices for Tuesday

Neither option is approved

Retain the agreed design

Celia authorises an additional £300.

£8,700 forecast

Requires the budget to increase from £8,400.

Approve the simpler border

Changes the agreed design; priced saving of £450.

£8,250 forecast

Leaves £150 below the existing £8,400 budget.

Without a recorded choice by 12:00 on 13 October, Suki will hold the 14 October paint order. Any resulting completion-date movement is unquantified. The £450 saving is an option, not money already saved. [M4, M5]

Last week’s commitments

Colour studyComplete
Oren finished on 7 October as promised. Celia confirmed on 8 October that it matches the agreed design. This accepts the study, not the mural. [M1, M4]
Equipment quoteComplete
Suki obtained the firm quote by 9 October as promised. Remaining hire is £1,650, replacing the £1,000 allowance. [M1, M3]
Invoice reconciliationComplete
Kit reconciled invoices on 8 October as promised; Friday’s actual spend is £4,250. [M1, M2]
Revised forecastProvided
Celia’s requested revision is available above. No budget increase or spend beyond the limit has been authorised. [M1–M3]
Caption wordingStill open
Expected last week, but no owner or deadline was recorded. Oren will raise it at Monday’s team meeting; ownership of final wording remains unassigned. [M1, M4, M5]

Separate uncertainty from the overrun

The £300 overrun is already in the forecast. A further coat is a different, unpriced risk: all estimates assume no coat beyond the revised paint quantity. If another coat is needed, materials costs may rise; no price is supplied. [M3, M5]

What the border option establishes

Oren says a simpler border would preserve the central image. It still changes the agreed design. There is no measured evidence of residents’ preference for it. [M4]