Weekly update · June 1–5, 2026

Canopy Reading Room

June 19 opening remains at risk

Lighting inspection and an acoustic test are still outstanding. The opening target has not moved; readiness is not confirmed.

Board decision needed by June 8

Project lead Asha asks the board to approve £600 for an acoustic test. Spending is not yet approved.

Furniture received

Inventory progress only; this does not measure overall readiness.

Last week8 of 16 pieces
This week12 of 16 pieces

Next work

June 10 · Lighting inspection
Contractor Leo expects to inspect on June 10. The inspection is pending.

June 12 · Readiness check
The next check will revisit opening readiness.