Canopy Reading Room
June 19 opening remains at risk
Lighting inspection and an acoustic test are still outstanding. The opening target has not moved; readiness is not confirmed.
Board decision needed by June 8
Project lead Asha asks the board to approve £600 for an acoustic test. Spending is not yet approved.
Furniture received
Inventory progress only; this does not measure overall readiness.
Last week8 of 16 pieces
This week12 of 16 pieces
Confirmed
Shelving is complete.
The access walkthrough passed.
Next work
June 10 · Lighting inspection
Contractor Leo expects to inspect on June 10. The inspection is pending.
June 12 · Readiness check
The next check will revisit opening readiness.